Board of Trustees Los Angeles Community College District |
ACTION |
|
|
|
Com. No. BSD4 |
Division Operations Division—Business Services |
Date June 25, 2003 |
Subject: FACILITIES
PLANNING AND DEVELOPMENT ROUTINE REPORT
PROPOSITION A PROJECTS
I. AUTHORIZE SERVICE AGREEMENTS
A. Authorize an agreement
with Albert + Rachlin Architects Group to provide architectural design and
engineering for the Jefferson Hall modernization project at Los Angeles City
College during the period July 1, 2003
through December 31, 2006 at a cost not to exceed $355,000 inclusive of
eligible reimbursable expenses.
Background: The Master Plan at Los Angeles City College
provides for the modernization of Jefferson Hall at Los Angeles City
College. Albert + Rachlin Architects
has been selected to provide design and engineering services for this project
from among architects responding to the on-call architectural services RFQ
posted on the Proposition A website.
Funding is through Proposition A bond proceeds. Jefferson Hall 01C.6111.03.
B.
Authorize an agreement with
Arquitectonica for programming, architectural design, engineering and construction
administration for the Fine and Performing Arts Complex project at East Los
Angeles College during the period July
1, 2003 through July 1, 2006, at a cost not to exceed $3,793,197 inclusive of
eligible reimbursable expenses.
Background: The Master Plan at East Los Angeles College
provides for the construction of a new Fine and Performing Arts Complex. Arquitectonica has been selected to provide
programming, architectural design, engineering and construction administration
for the project from among architectural firms responding to a Request for
Qualifications posted on the Proposition A website for this project. The building will be reviewed by a committee
of the Board of Trustees for LEEDS ™ applicability. Funding is through Proposition A bond proceeds. Fine and Performing Arts Complex
02E.6207.02.
C.
Authorize an agreement with
RAW/WWCOT for architectural programming for the Student Services/Activities
Cluster at Los Angeles Southwest College
during
the period July 1, 2003 through January 31, 2004, at a cost not to exceed
$151,000 inclusive of eligible reimbursable expenses.
Background: The Master Plan at Los Angeles Southwest
College provides for the construction of a Student Services/Activities
Cluster. RAW/WWCOT has been selected to
provide architectural programming for the project from among architectural
firms responding to Request for Qualifications for architectural programming
posted on the Proposition A website.
Funding is through Proposition A bond proceeds. Student Services/Activities Cluster
06S.6606.02.
D.
Authorize an agreement with
Hellmoth, Obata & Kassabaum, Inc. for architectural design and engineering
for the Science and Math Building at West Los Angeles College during the period July 1, 2003 through November 1,
2006, at a cost not to exceed $2,099,526 inclusive of eligible reimbursable
expenses.
Background: The Master Plan at West Los Angeles College
provides for the construction of a new Science and Math Building. Hellmoth, Obata &Kassabaum, Inc., (HOK)
has been selected to provide architectural design, engineering and construction
administration for the project from among aurchitectural firms responding to a
Request for Qualifications posted on the Proposition A website for this
project. The building will be reviewed
by a committee of the Board of Trustees for LEEDS ™ applicability. Funding is through Proposition A bond
proceeds. Science and Math Building
09W.6905.02.
II. RATIFY SERVICE AGREEMENTS
A. Ratify Amendment No. 1
to Agreement No. 30253 with Fields Devereaux Architects and Engineers to
provide additional architectural services in the Holmes Hall modernization
project at Los Angeles City College during
the period June 11, 2003 through November 10, 2003 at a cost not to exceed
$25,010 inclusive of eligible reimbursable expenses.
Background: This agreement was ratified by the Board of
Trustees on October 9, 2002 (Com. No. BSD4).
Under the original agreement Fields Devereaux Architects and Engineers
was retained to provide architectural and engineering services for the Holmes
Hall modernization at Los Angeles City College. Additional services are required to incorporate the “smart”
classroom into an enlarged space, provide key card access and add various
enhancements. The revised contract
amount including this amendment is $92,010.
Funding is through Proposition A bond proceeds. Holmes Hall Modernization 01C.6110.03.
B. Ratify Amendment No. 2
to Agreement No. 30154 with Robbins Jorgensen Christopher to provide additional
design services for modernization projects at Los Angeles Harbor College during the period June 6, 2003 through July 31, 2003
at a cost not to exceed $7,900 inclusive of eligible reimbursable
expenses.
Background: This agreement was ratified by the Board of
Trustees on July 10, 2002, (Com. No. BSD4).
Under the original agreement, Robbins Jorgensen Christopher was retained
to provide architectural programming services for the modernization of a number
of buildings at Los Angeles Harbor College.
Additional services are required to add the services of a civil engineer
to the Robbins Jorgensen Christopher team to investigate underground utilities
including the sewer line and performing other site utility improvements. The revised contract amount including this
amendment is $502,847. Funding is
through Proposition A bond proceeds.
Site Utilities 03H.6337.03.
C. Ratify Amendment No. 1
to Agreement No. 30266 with Terry A. Hayes Associates LLC to provide additional
services in the preparation of the Environmental Impact Report (EIR) for Los
Angeles Southwest College during the
period November 22, 2002 through October 31, 2003 at a cost not to exceed
$2,500 inclusive of eligible reimbursable expenses.
Background: This agreement was ratified by the Board of
Trustees on November 20, 2002 (Com. No. BSD4).
Under the original agreement Terry A. Hayes Associates LLC was retained
to prepare the EIR for Los Angeles Southwest College. Additional services are required to draft additional required
provisions of the EIR not included in the original scope of services. The revised contract amount including this
amendment is $158,470. Funding is through
Proposition A bond proceeds.
Environmental Impact Report 06S.6681.01.
D. Ratify Amendment No. 1
to Agreement No. 30359 with A. C. Martin Partners, Inc. to provide additional
design services for the Lot 8 Parking Structure at West Los Angeles College during the period July 1, 2003 through September 30,
2003 at a cost not to exceed $27,850 inclusive of eligible reimbursable
expenses.
Background: This agreement was ratified by the Board of
Trustees on March 12, 2003 (Com. No. BSD4).
Under the original agreement, A. C. Martin Partners, Inc. provided
architectural and engineering services for the new Lot 8 Parking Structure at
West Los Angeles College. Additional
design services are required to add photo voltaic studies and to incorporate an
electronic vehicle charging stations in the design. The revised contract amount including this amendment is
$850,991. Funding is through
Proposition A bond proceeds. Lot 8
Parking Structure 09W.6905.02.
III. AUTHORIZE CONSTRUCTION CONTRACTS
A. Authorize a construction contract with
Air-Ex Air Conditioning, Inc., for the Bailey Library
Electrical and Mechanical upgrade project at East Los Angeles College at a cost of $1,700,000.
Background: This construction contract is the result of
formal bidding. Ten (10) bidders requested bid packages. Four (4) responsive bids were received ranging from $1,700,000 to $____. Funding is through Proposition A bond proceeds. Bailey Library Upgrades 02E.6212.03.
B. Authorize a construction contract with
Astro Painting for the campuswide painting
project at Los Angeles Harbor College at a cost of $494,000.
Background: This construction contract is the result of
formal bidding. Twenty two (22) bidders requested bid
packages. Two (2) responsive bids were received ranging from $494,000 to
$627,100. Funding is through
Proposition A bond proceeds. Campuswide painting 03H.6310.03.
IV. RATIFY CONSTRUCTION CONTRACTS
A. Ratify a construction order with Build Masters to perform
certain items of work in the scope of Prime Painting Contractors, Inc. on the
Clausen Hall DSPS project at Los Angeles City College for the sum of $13,500.
Background: Build Masters provided the low quote to
perform items of work on the punchlist of Prime Painting Contractors, Inc. at
Los Angeles City College. Funding is
through Proposition A bond proceeds.
Clausen Hall DSPS $13,500.
V. RATIFY
CONSTRUCTION CONTRACT CHANGE ORDERS
A. Ratify Change Order No. 2 to Agreement
No. 30174 with Prime Painting Contractors, Inc. for certain additional items of
work on the DSPS project in Clausen Hall at Los Angeles City College at a cost
of 10,254, assess liquidated damages of $9,500 on Prime Painting for delay, to
assess a penalty in the amount of $33,812 for violations of the Subcontractor
List Law set forth in Public Contract Code section ___ and to deduct $13,500
from the scope of work to be performed by Prime Painting Contractors, Inc. for
a total deductive change order of $46,558.
Background:
This agreement was authorized by the Board of Trustees on May 9, 2001 (Com No. BSD10). The additive portion of this change order is
for additional painting. The deductive
portion of this change order is to assess necessary and appropriate penalties
upon the contractor. Total change
orders to date including this change order total 10.5% of the original
contract. This project totals
$447,700.30 including this deductive change order. Funding is through Proposition A bond proceeds. Clausen Hall DSPS 01C.6107.03.
B. Ratify Change Order No. 1 to Agreement
No. 30229 with Kahromic Contracting, Inc. for additional general construction
work on the project to provide electrical and HVAC service to the switchroom
for the new telephone system at Los Angeles Harbor College for the total price
of $1,597.35.
-
Relocate transformer disconnect switch and electrical panel
-
Provide additional ground cable
Background:
This agreement was authorized by the Board of Trustees on May 9, 2001 (Com No.
BSD10). This change order is to perform
additional scope. All change orders
approved to date including this change order total 9.18% of the original
contract. This project totals
$18,997.35 including this change order.
Funding is through Proposition A bond proceeds. Electrical Power Supply and Grounding for
Phone System 03H.6379.03.
VI. RATIFY PURCHASE ORDERS
A. Ratify
a purchase order with M3LLC to provide furniture for the Holmes Hall
modernization project at Los Angeles City College at a cost of $53,950.78.
Background: M3 LLC provided the low quote to provide
furniture and coordinate installation for the Holmes Hall modernization project
at Los Angeles City College Funding is through Proposition A bond
proceeds. Holmes Hall Modernization
01C.6110.03.
|
|
Chancellor and Secretary to the Board of Trustees
By:______________________________ Date_________________
|
Candaele ___________ Pearlman ___________ Field _______________ Scott-Hayes_________ Furutani__ __________ Waxman____________ Mercer _____________ McMullen___________ Student Trustee Advisory Vote |