Board of TrusteesLos Angeles Community College District |
ACTION |
|
|
|
Com. No. BSD4 |
Division Operations—Business Services |
Date August 20, 2003 |
Subject: FACILITIES
PLANNING AND DEVELOPMENT ROUTINE REPORT
PROPOSITION
A PROJECTS
Subject:
I. AUTHORIZE SERVICE AGREEMENTS
A. Authorize an agreement with Quatro Design
Group to provide architectural design, engineering and construction
administration services for the Student Services Modernization project at East
Los Angeles College during the period August 21, 2003 through August 1, 2005 at
a cost not to exceed $682,693 inclusive of reimbursable expenses.
Background: The Master Plan at East Los Angeles College
provides for the modernization of the Student Services Center. Quatro Design Group has been selected to
perform architectural and engineering design from among architectural firms
responding to a Request for Qualifications posted on the Proposition A
website. Funding is through Proposition
A bond proceeds. Student Services
Center Modernization 02E.6213.03.
B. Authorize an agreement with Kleinfelder,
Inc. to provide inspection and testing services on an on-call basis at all
District campuses during the period August 21, 2003 through July 31, 2004 at a
cost not to exceed $250,000 inclusive of reimbursable expenses.
Background: The Proposition A program will require that
DSA certified inspectors be sent at construction sites. Kleinfelder, Inc. has responded to a Request
for Qualifications posted on the Proposition A website for firms which provide
such services on an on-call basis, and is qualified to render such
services. Funding is through Proposition
A bond proceeds. Districtwide Inspections & Testing 10D.6096.05.
C. Authorize an agreement with Tri/Con
Engineering, Inc. to provide inspection and testing services on an on-call
basis at all District campuses during the period August 21, 2003 through July
31, 2004 at a cost not to exceed $250,000 inclusive of reimbursable expenses.
Background: The Proposition A program will require that
certified inspectors be present at construction sites. Tri/Con Engineering, Inc. has responded to a
Request for Qualifications posted on the Proposition A website for firms which
provide such services on an on-call basis, and is qualified to rendered such
services. Funding is through
Proposition A bond proceeds. Districtwide Inspections & Testing 10D.6096.05.
II. RATIFY SERVICE AGREEMENTS
A. Ratify an agreement with
Leidenfrost/Horowitz & Associates to provide architectural design and
engineering services to create swing space within the cafeteria building at Los
Angeles City College during the period January 6, 2003 through May 2, 2003 at a
cost not to exceed $7,250 inclusive of eligible reimbursable expenses.
Background: Swing space in the cafeteria building at Los
Angeles City College is required to support the Proposition A bond
program. Leidenfrost/Horowitz &
Associates has been selected from among qualified architectural firms to plan
and design such space and to prepare construction drawings and DSA
documentation. Funding is through
Proposition A bond proceeds. Relocation
and/or Acquisition of Temporary Facilities 01C.6177.04.
B. Ratify an agreement with Diana Ho
Consulting Group to provide professional services in support of mitigation
measures required in the Final Environmental Impact Report (EIR) at Los Angeles
City College during the period August 1, 2003 through December 31, 2003 at a
cost not to exceed $49,490 inclusive of eligible reimbursable expenses.
Background: The Final EIR at Los Angeles City College
requires traffic mitigation measures.
Diana Ho Consulting Group will provide research and recommendations
regarding the possible institution of MTA’s
Universal Pass Program to increase use of mass transit by staff and
students at Los Angeles City College.
Funding is through Proposition A bond proceeds. Other Consulting Services 01C.6195.05.
C. Ratify Amendment No. 1 to Agreement No.
30202 with Geocon Consultants, Inc. to provide additional geotechnical services
in support of the Math, Science and Technology Building project at Los Angeles
City College during the period August 15, 2003 through September 15, 2003 at a
cost not to exceed $8,000 inclusive of eligible reimbursable expenses.
Background: This agreement was ratified by the Board of
Trustees on September 18, 2002 (Com. No. BSD4). Under the original agreement, Geocon Consultants, Inc. was
retained to provide a soils report and geologic/seismic study for the Math,
Science and Technology Building at Los Angeles City College which is generally
located above the tunnel for the Red Line operated by the Los Angeles County
Metropolitan Transit Agency (LACMTA).
Additional professional services are required to provide soils
calculations and other items required by LACMTA. The total amount of this agreement including this amendment is
$20,000. Funding is through Proposition
A bond proceeds. Math, Science and
Technology Building 01C.6101.02.
D. Ratify Amendment No. 1 to Agreement No. 30199 with the Smith Group to
provide architectural and engineering design services for the Math, Science and
Technology Building at Los Angeles City College during the period August 15, 2003
through September 15, 2003 at a cost not to exceed $25,000 inclusive of
eligible reimbursable expenses.
Background: This agreement was authorized by the Board
of Trustees on August 14, 2002 (Com. No. BSD4). Additional architectural and engineering services are required to
redesign the building foundations to alleviate pressure on the adjacent MTA
tunnel and blast shafts to ensure the structural integrity of the Math, Science
and Technology Building and MTA’s structure.
The total of this agreement including this amendment is $2,371,000. Funding is through Proposition A bond
proceeds. Math, Science and Technology
Building 01C.6101.02.
E. Ratify Amendment No. 2 to Agreement No. 30253
with Fields Devereaux Architects & Engineers to provide additional
architectural and engineering services for the Holmes Hall Modernization
project at Los Angeles City College during the period August 20, 2003 through
February 16, 2004 at a cost not to exceed $33,825 inclusive of eligible
reimbursable expenses.
Background: This agreement was authorized by the Board
of Trustees on October 9, 2002 (Com. No. BSD4). Additional architectural and engineering services are required to
design additional operable windows and motorized dampers, retrofit the
multi-zone office complexes, investigate retrofitting the existing rooftop
outside air handler, retrofit the classroom fan coil units, and incorporate
campus security standards. The total of
this agreement including this amendment is $125,835. Funding is through Proposition A bond proceeds. Holmes Hall Modernization 01C.6110.03.
F. Ratify Amendment No. 2 to Agreement No. 30265
with Horiuchi & Associates to provide additional design, engineering and
architectural construction administration services for the F, G & H Electrical
and Mechanical Upgrades project at East Los Angeles College during the period
August 1, 2003 through August 1, 2004 at a cost not to exceed $10,500 inclusive
of eligible reimbursable expenses.
Background: This agreement was authorized by the Board
of Trustees on November 20, 2002 (Com. No. BSD4). Additional design, engineering, and architectural construction
administration services are required to modify Building G-3’s foyer air
distribution system in order to provide a separate temperature and humidity
controlled environment, independent of the central building air conditioning
system. The upgrade is required at
Building G-3 so that the Mural Art Work located in the foyer can be maintained
at the proper temperature and humidity on a 24-hour basis without using the
150-ton building chiller. The total of
this agreement including this amendment is $151,500. Funding is through Proposition A bond proceeds. F, G & H Electrical and Mechanical
Upgrades 02E.6279.03.
G. Ratify Amendment No. 1 to Agreement No. 30373
with Psomas to provide additional hydrology studies necessary to support
preparation of the Environmental Impact Report (EIR) at Los Angeles Mission
College during the period August 21, 2003 through September 21, 2003 at a cost
not to exceed $34,500 inclusive of eligible reimbursable expenses.
Background: This agreement was ratified by the Board of
Trustees on March 26, 2003 (Com. No. BSD4).
Under the original agreement Psomas was retained to prepare an EIR level
study and a storm drain water quality management plan. As a result of an expansion in the scope of
the EIR, more detailed hydrology studies and water quality analysis are
required, the project area has been expanded and increased coordination with
the EIR consultant, the U. S. Army Corps of Engineers and county
representatives and the public will be necessary. The total of this agreement including this amendment is
$82,800. Funding is through Proposition
A bond proceeds. Soil Testing
04M.6483.01.
H. Ratify an agreement with Psomas to provide
surveying and monitoring services for the Student Store/Financial Aid Building
project at Los Angeles Pierce College during the period August 4, 2003 through
February 4, 2006 at a cost not to exceed $9,100 inclusive of eligible reimbursable
expenses.
Background: As a result of soil conditions at the site
of the Student Store/Financial Aid Building at Los Angeles Pierce College,
survey and elevation monitoring is required by the Division of the State Architect (DSA). Psomas has been retained from among qualified consultants to
provide a monthly report of the results of monitoring activity. Funding is through Proposition A bond
proceeds. Student Store/Financial Aid
Building 05P.6504.02.
I. Ratify Amendment No. 1 to Agreement No. 30392
with La Canada Design Group to provide additional design services for the Plant
Facilities/Sheriffs’ Station project at Los Angeles Valley College during the
period July 17, 2003 through June 30, 2004 at a cost not to exceed $7,931
inclusive of eligible reimbursable expenses.
Background: This Agreement was authorized by the Board
of Trustees on April 9, 2003 (Com. No. BSD4).
Additional architectural/engineering services are required to design
efficient storage for the Maintenance and Operations shops and for the
shipping/receiving department, both of which will be located inside the new
Maintenance and Operations building complex.
The total of this agreement including this amendment is $575,682. Funding is through Proposition A bond
proceeds. Plant Facilities/Sheriffs’
Station 08V.6805.02.
III. RATIFY CONSTRUCTION CONTRACT CHANGE
ORDERS
A. Ratify Construction Contract Change Order
No. 1 to Contract No. 30360 with Kahromic Contracting, Inc. in the amount of
$18,329 for the following action for the Demolition of Temporary/Obsolete
Facilities.
- remove extra asphalt on tennis courts
(additive $9,806)
- temporary fencing included in the original
contract not required (deductive $9,000)
- digging three trenches and relocation of the
gas line (additive $17,523).
Background: This contract was authorized by the Board of
Trustees on March 12, 2003 (Com No. BSD4).
This change order is due to work not in the original scope of the
contractor. This project totals $249,329
with this change order or 8% of the original contract amount of $231,000. Funding is through Proposition A bond
proceeds. Demolition of
Temporary/Obsolete Facilities 01C.6176.02.
B. Ratify Construction Contract Change Order
No. 1 to Contract No. 30389 with Byrom-Davey, Inc. in the amount of $32,810 for
the PE Fields Renovation project at East Los Angeles College.
- saw cut a 6” wide section of swale and
asphalt paving around the outside perimeter of the track
- install a 6” X 12” concrete curb around the
perimeter of the track
- increase the project duration by four
calendar days
Background: This contract was authorized by the Board of
Trustees on April 9, 2003 (Com No. BSD4).
This change order is due to work not in the original scope of the
contractor. This project totals
$946,502 or 3.6% of the original contract amount of $913,692. Funding is through Proposition A bond
proceeds. PE Fields Renovation
02E.6211.03.
IV. AUTHORIZE ACCEPTANCE OF COMPLETION
OF CONSTRUCTION CONTRACTS
Authorize
the Acceptance of Completion for Contract No. 30425 with Prime Painting
Contractors, Inc. for the Relocation of the Transfer Center and Maintenance and
Operations at Los Angeles City College with a substantial completion date of
January 27, 2003.
Background: This contract was approved by the Board of
Trustees on May 28, 2003 (Com No. BSD4).
This project totaling $23,357 is funded by Proposition A bond proceeds. Relocation and/or Acquisition of Temporary Facilities
01C.6177.04.
|
|
Chancellor and Secretary to the Board of Trustees
By:______________________________ Date________________ |
Candaele ____________ Pearlman ______________ Field ________________ Scott-Hayes____________ Furutani _____________ Waxman_______________ Mercer _______________ McMullen_______________ Student Trustee Advisory Vote |